Question

1 Approved Answer

Activity B has a Finish to Finish relationship including a 3 day lag with it's predecessor A. A has an ES of 12 and a

Activity B has a Finish to Finish relationship including a 3 day lag with it's predecessor A. A has an ES of 12 and a duration of 8. B has a duration of 10, what is the EF for B?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MGMT Principles Of Management

Authors: Chuck Williams

11th Edition

133740747X, 9781337407472

More Books

Students also viewed these General Management questions

Question

What is a fixed menu? a cycle menu?

Answered: 1 week ago

Question

Relax your shoulders

Answered: 1 week ago