Question

1 Approved Answer

Activity C on a CPM network has predecessor B , and has successors D and F . C has duration 7 days. B ' s

Activity C on a CPM network has predecessor B, and has successors D and F. C has duration 7 days. B's earliest finish is 20. D's late start is 30, while F's is 27. Which of the following is definitely TRUE?
Group of answer choices
D has no slack and is critical..
C is completed before B.
F has slack and is not critical.
B has slack and is not critical.
C has no slack and is critical.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality An Introduction

Authors: Robert A Brymer, Misty M Johanson

14th Edition

0757588638, 9780757588631

More Books

Students also viewed these General Management questions