Activity Cost Pool Activity Driver Driver Quantity Setup $ 100,000.00 Number of setups 500.00 Order Fulfillment $ 40,000.00 Number of orders 3,200.00 Maintenance $ 200,000.00
Activity | Cost Pool | Activity Driver | Driver Quantity |
Setup | $ 100,000.00 | Number of setups | 500.00 |
Order Fulfillment | $ 40,000.00 | Number of orders | 3,200.00 |
Maintenance | $ 200,000.00 | Machine hours | 4,000.00 |
Power | $ 20,000.00 | Kilowatt hours | 80,000.00 |
Following two jobs are completed during the year:
Job CC | Job DD | |
Direct materials | $ 375.00 | $1,000 |
Direct labor | $ 350.00 | $1,200 |
Units as part of job | 100 | 160 |
Direct labor hours | 50 | 80 |
Number of setups | 1 | 4 |
Number of orders | 4 | 5 |
Machine hours | 20 | 25 |
Kilowatt hours | 30 | 50 |
The company budgets 4,000 direct labor hours.
Using job-order costing, what is the unit cost for Job CC (rounded to cents, if needed)?
(Use direct labor hours as the cost driver, and assume none of the overhead costs listed are SG&A costs)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started