Question

1 Approved Answer

Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3 Side 1 S-----------F Complete Spent $2,000 Side 2 S--------PF ----F Complete

Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3
Side 1 S-----------F Complete Spent $2,000
Side 2 S--------PF ----F Complete Spent $2,200
Side 3 PS--S------PF 40% done, spent $1,000
Side 4 PS---------PF Not yet started
Key S= Actual Start, F=Actual Finish, PS=Planned Start and PF=Planned Finish

Earned Value Management (EVM): You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for $2000 per side. The sides are planned to be completed one after the other. Today is the end of day 3. What is the Cost Performance Index (CPI)?

a.

0.88

b.

0.93

c.

0.80

d.

0.92

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions