1 Approved Answer
Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser
Activity | Description | Immediate Predecessor | Optimistic | Most Probable | Pessimistic |
---|---|---|---|---|---|
A | Meet with board | 1 | 1 | 2 | |
B | Hire coaches | A | 4 | 6 | 8 |
C | Conduct fundraiser | A | 2 | 4 | 6 |
D | Announce program | B, C | 1 | 2 | 3 |
E | Meet with coaches | B | 2 | 3 | 4 |
F | Order team equipment | A | 1 | 2 | 3 |
G | Register athletes | D | 1 | 2 | 3 |
H | Reserve buses for meets | G | 1 | 2 | 3 |
I | Plan first practice | E, H, F | 1 | 1 | 1 |
Develop an activity schedule. (Round your answers to two decimal places.)
Activity | Earliest Start | Latest Start | Earliest Finish | Latest Finish | Slack |
---|---|---|---|---|---|
A | See the rounding prompt for how many decimal places are needed. | ||||
B | See the rounding prompt for how many decimal places are needed. | See the rounding prompt for how many decimal places are needed. | See the rounding prompt for how many decimal places are needed. | ||
C | See the rounding prompt for how many decimal places are needed. | ||||
D | See the rounding prompt for how many decimal places are needed. | See the rounding prompt for how many decimal places are needed. | |||
E | |||||
F | See the rounding prompt for how many decimal places are needed. | See the rounding prompt for how many decimal places are needed. | |||
G | See the rounding prompt for how many decimal places are needed. | ||||
H | |||||
I |
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
F,A,E,G,D,H,I
What is the expected project completion time (in weeks)? (Round your answer to two decimal places.)
weeks
(d)
If the athletic director plans to start the project on January 1, calculate the probability the track and field team will be ready by the scheduled April 1 date (13 weeks) based solely on the critical path. (Round your answer to four decimal places.)
Should the athletic director begin planning the track and field team before January 1? (The proba
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started