Question

1 Approved Answer

Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser

Activity Description Immediate
Predecessor
Optimistic Most Probable Pessimistic
A Meet with board 1 1 2
B Hire coaches A 4 6 8
C Conduct fundraiser A 2 4 6
D Announce program B, C 1 2 3
E Meet with coaches B 2 3 4
F Order team equipment A 1 2 3
G Register athletes D 1 2 3
H Reserve buses for meets G 1 2 3
I Plan first practice E, H, F 1 1 1
Develop an activity schedule. (Round your answers to two decimal places.)
Activity Earliest
Start
Latest
Start
Earliest
Finish
Latest
Finish
Slack
A
See the rounding prompt for how many decimal places are needed.
B
See the rounding prompt for how many decimal places are needed.

See the rounding prompt for how many decimal places are needed.

See the rounding prompt for how many decimal places are needed.
C
See the rounding prompt for how many decimal places are needed.
D
See the rounding prompt for how many decimal places are needed.

See the rounding prompt for how many decimal places are needed.
E
F
See the rounding prompt for how many decimal places are needed.

See the rounding prompt for how many decimal places are needed.
G
See the rounding prompt for how many decimal places are needed.
H
I
(c)
What are the critical activities? (Enter your answers as a comma-separated list.)
F,A,E,G,D,H,I
What is the expected project completion time (in weeks)? (Round your answer to two decimal places.)
weeks
(d)
If the athletic director plans to start the project on January 1, calculate the probability the track and field team will be ready by the scheduled April 1 date (13 weeks) based solely on the critical path. (Round your answer to four decimal places.)
Should the athletic director begin planning the track and field team before January 1? (The proba

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render, Paul Griffin

1st Canadian Edition

132687585, 978-0133357516, 133357511, 978-0132687584

More Books

Students also viewed these General Management questions