Activity II: A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities,

Activity II: A project has 11 activities that can be accomplished either by one person working alone or by several people working together. The activities, precedence constraints, and time estimates are given in Table below. Suppose that you have up to five people who can be assigned on any given day. A person must work full days on each activity, but the number of people working on an activity can vary from day to day.

Activity

Immediate predecessors

Person-days required

A

10

B

A

8

C

A

5

D

B

6

E

D

8

F

C

7

G

E,F

4

H

F

2

I

F

3

J

H,I

3

K

J,G

2

  1. Prepare an AOA network diagram, and calculate the critical path, total slacks, and free slacks assuming that one person (independently) is working on each task.
  2. Prepare an early-start Gantt chart.
  3. Prepare a daily assignment sheet for personnel with the goal of finishing the project in the minimum amount of time.
  4. Prepare a daily assignment sheet to best balance the workforce assigned to the project.
  5. By how many days could the project be compressed if unlimited personnel resources were available?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing A Practical Approach

Authors: Robyn Moroney, Fiona Campbell, Jane Hamilton, Valerie Warren

3rd Canadian edition

1-119-40285-5, 111940276X, 978-1119566007

More Books

Students also viewed these Accounting questions