Question

1 Approved Answer

Activity Immediate Predecessor Normal time Normal Cost (FD) Crashing Time Crashing Cost (FD) A - 3 150 3 150 B - 4 200 3 220

Activity

Immediate Predecessor

Normal time

Normal Cost (FD)

Crashing Time

Crashing Cost (FD)

A

-

3

150

3

150

B

-

4

200

3

220

C

A

4

500

3

575

D

A,B

5

300

3

400

E

C,D

5

400

4

550

F

E,D

3

200

2

600

  1. Draw the AON diagramme for the above schedule.
  2. Calculate crash cost per day for each activity
  3. What is the estimated completion time?
  4. What is the best option to crash the project to complete in 1 day earlier?
  5. What are the best options to crash the project to complete in 2 days earlier?
  6. What are the best options to crash the project to complete in 3 days earlier?

What are the best options to crash the project to complete in 4 days earlier?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard Lynch

5th Edition

0273716387, 978-0273716389

More Books

Students also viewed these General Management questions