Question
1 Approved Answer
Activity Immediate Predecessor Normal time Normal Cost (FD) Crashing Time Crashing Cost (FD) A - 3 150 3 150 B - 4 200 3 220
Activity | Immediate Predecessor | Normal time | Normal Cost (FD) | Crashing Time | Crashing Cost (FD) |
A | - | 3 | 150 | 3 | 150 |
B | - | 4 | 200 | 3 | 220 |
C | A | 4 | 500 | 3 | 575 |
D | A,B | 5 | 300 | 3 | 400 |
E | C,D | 5 | 400 | 4 | 550 |
F | E,D | 3 | 200 | 2 | 600 |
- Draw the AON diagramme for the above schedule.
- Calculate crash cost per day for each activity
- What is the estimated completion time?
- What is the best option to crash the project to complete in 1 day earlier?
- What are the best options to crash the project to complete in 2 days earlier?
- What are the best options to crash the project to complete in 3 days earlier?
What are the best options to crash the project to complete in 4 days earlier?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started