Activity Immediate Predecessor Optimistic Most Likely Pessimistic Sigma Variance A - 2 3 4 0 . 3 3 3 0 . 1 1 1 B
Activity
Immediate
Predecessor
Optimistic
Most
Likely
Pessimistic
Sigma
Variance
A
B
C
A
D
A
E
B C
F
B
G
D E
H
G F
Which activities are part of the critical path?
a ABEGH
b CDE
c ACEGH
d BFH
e ADGH