Activity Immediate Predecessor Time in Days A None 3 B A 2 C A 1 D B and C 3 E D 4 What is
Activity Immediate Predecessor Time in Days
A None
B A
C A
D B and C
E D
What is the Latest Finish Time for the last activity in this project ie the total time to complete the project