Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Activity Immediate Time (weeks) Predecesso Optimistic Most Probable Pessimistic r A 1.5 2.0 2.5 B A 2.0 2.5 6.0 C 1.0 2.0 3.0 D

imageimage

Activity Immediate Time (weeks) Predecesso Optimistic Most Probable Pessimistic r A 1.5 2.0 2.5 B A 2.0 2.5 6.0 C 1.0 2.0 3.0 D C 1.5 2.0 2.5 EFGH B, D 0.5 1.0 1.5 E 1.0 2.0 3.0 B, D 3.0 3.5 7.0 G 3.0 4.0 5.0 - F, H 1.5 2.0 2.5 a. Draw a project network. b. What are the critical activities and what is the expected project completion time? c. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project? Due Date: Apr 12, 11:59pm 2. Doug Casey is in charge of planning and coordinating next spring's sales management training program for his company. Doug listed the following activity information for this project:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Holt McDougal Larson Geometry

Authors: Ron Larson, Laurie Boswell, Timothy D. Kanold, Lee Stiff

1st Edition

0547315171, 978-0547315171

More Books

Students also viewed these General Management questions