Question: Doug Casey is in charge of planning and coordinating next springs sales management training program for his company. Doug listed the following activity information for

Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:


Doug Casey is in charge of planning and coordinating next


a. Draw a project network.
b. Prepare an activity schedule.
c. What are the critical activities and what is the expected project completion time?
d. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on theproject?

Time (weeks) Immediate Predecessor Optimistic Most Probable Pessimistic Activity Description Plan topic Obtain speakers List meeting locations Select location Finalize speaker travel plans Make final check with speakers Prepare and mail brochure Take reservations Handle last-minute details 2.0 2.5 6.0 1.0 1.5 0.5 B, D B, D F. H 2.0 2.0 1.0 2.0 3.5 4.0 3.0 5.0 1.5

Step by Step Solution

3.40 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Activity Expected Time Variance A 2 003 B 3 044 C 2 011 D ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

148-M-S-Q-M (45).docx

120 KBs Word File

Students Have Also Explored These Related Statistics Questions!