Question

1 Approved Answer

Activity numbering systems in Project Networks should: Group of answer choices ensure each activity gets a unique identification code leave gaps ( using non -

Activity numbering systems in Project Networks should:
Group of answer choices
ensure each activity gets a unique identification code
leave gaps (using non-consecutive numbers) in the numbering system so that missing or new activities may be added to the network later if they are needed
be ascending as movement from left to right through the project network occurs
be as simple as possible to avoid confusion
all of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

AWS Certified Database Study Guide Specialty DBS-C01 Exam

Authors: Matheus Arrais, Rene Martinez Bravet, Leonardo Ciccone, Angie Nobre Cocharero, Erika Kurauchi, Hugo Rozestraten

1st Edition

1119778956, 978-1119778950

More Books

Students also viewed these Databases questions

Question

What is DDL?

Answered: 1 week ago