Question
1 Approved Answer
Activity numbering systems in Project Networks should: Group of answer choices ensure each activity gets a unique identification code leave gaps ( using non -
Activity numbering systems in Project Networks should:
Group of answer choices
ensure each activity gets a unique identification code
leave gaps using nonconsecutive numbers in the numbering system so that missing or new activities may be added to the network later if they are needed
be ascending as movement from left to right through the project network occurs
be as simple as possible to avoid confusion
all of the above