Activity Optimistic Most likely pessimistic A 5 7 12 B 4 9 10 C 2 3 4 D 6 12 18 34)What is expected completion
Activity
Optimistic
Most likely
pessimistic
A
5
7
12
B
4
9
10
C
2
3
4
D
6
12
18
34)What is expected completion time for activity D?
A.12.000
B.12.667
C.12.333
D.13.152
35)What is the variance for activity A?
A.1.000
B.1.361
C.5.444
D.4.315
36)If activities A, B and D are on the critical path, what is the probability of completing the project in less than 26 days?
A.0.2190
B.0.2336
C.0.7125
D.0.1245
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started