Activity Preceding Time A -- 8 B -- 4 C B 3 D A 3 E A, C 3 F D, E 4 (1) Please
Activity | Preceding | Time |
A | -- | 8 |
B | -- | 4 |
C | B | 3 |
D | A | 3 |
E | A, C | 3 |
F | D, E | 4 |
(1) Please draw the project network diagram based on the table above.