Question

1 Approved Answer

Activity Predecessor Duration ( weeks ) Budget Actual Cost Complete % a 2 3 0 0 4 0 0 1 0 0 b 3 2

Activity Predecessor Duration (weeks) Budget Actual Cost Complete %
a 2300400100
b 3200180100
c a 2250300100
d a 560040020
e b,c 440020020At week 6 the estimated cost of the project at completion (EAC) with no decimal places is calculated as ......
(Assume that the accuracy of the estimates to date has not been good and many of the assumptions made are no longer valid.)
Your Answer:
Question 15 options:
Answer

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Dynamics Systems Thinking And Modeling For A Complex World

Authors: John Sterman, John D. Sterman

1st Edition

007238915X, 9780072389159

More Books

Students also viewed these General Management questions

Question

Answered: 1 week ago

Answered: 1 week ago