Activity Predecessor Optimistic Most Likely Pessimistic Duration Standard Deviation Duration in Months A 4 7 10 B 7 5.5 7 C 25 33 41 D

Activity Predecessor Optimistic Most Likely Pessimistic Duration Standard Deviation
Duration in Months
A 4 7 10
B 7 5.5 7
C 25 33 41
D B 20 23 32
E C 1 2 15.5
F D 4 7 22
G A, B 22 10 10
H E 5 9 19
I G 4 3 26
J F, G 12 7 20

Use the information above and draw a network diagram showing the L/S, E/S, E/F, L/F, Slack, and Critical Path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Management

Authors: Chuck Williams

7th Edition

128586624X, 978-1285866246

More Books

Students also viewed these General Management questions

Question

Be able to cite the advantages of arbitration

Answered: 1 week ago