Question
Activity Predecessor/ relationship duration Execution month A ''-'' 3 1 B A(FS+S) 2 2 C A(SS+2) 1 2 D C(FF) 2 3 E B(SS+3) 5
Activity | Predecessor/ relationship | duration | Execution month |
A | ''-'' | 3 | 1 |
B | A(FS+S) | 2 | 2 |
C | A(SS+2) | 1 | 2 |
D | C(FF) | 2 | 3 |
E | B(SS+3) | 5 | 4 |
F | E(FS),D(FS) | 2 | 5 |
Let's make the assignment a little more interesting:
So far, we have only done network diagramming using basic forms of
dependency, and finish-to-Star (FS)
Today's assignment is to use other dependencies and still be able to
calculate some very interesting numbers.
For this, it is VERY important that you first watch the lecture and videos
on dependency exercises that I left on Canvas.
Note: I understand that what we are going to do by "Hand", is already
done by a software like MS Project, but it is IMPORTANT that you know
the mechanism behind the software code, the theory, the and basics.
According to the table below
Calculate:
1. Drawing the network diagram
2. Draw the Gantt Chart (you can see how to do it in the exercise
videos in week 7).
3. ES, EF, LS, LF, and the SL
4. The critical path in two ways, one as I taught you (looking for the
paths) and the other traditional way.
5. Calculate clearances / Free slack
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started