Activity R on a CPM network has predecessors M and N , ?and has successor S . ?R has duration 5 . ?N ' s

Activity R on a CPM network has predecessors M and N , ?and has successor S . ?R has duration 5 . ?N ' s late finish is 1 8 , ?while M ' s is 2 0 . ?S ' s late start is 1 4 . ?Which of the following is definitely true?
Select one:
a . ?N is a critical activity
b . ?R has no slack but is not critical
c . ?R is critical and has zero slack
d . ?S is a critical activity.
e . ?The set of times cannot all be possible.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Planning And Control Techniques

Authors: Rory Burke

3rd Edition

047198762X, 9780471987628

More Books

Students also viewed these General Management questions

Question

13. Give four examples of psychological Maginot lines.

Answered: 1 week ago