Question

1 Approved Answer

Activity Time ( weeks ) Immediate Predecessor ( s ) Activity Time ( weeks ) Immediate Predecessor ( s ) A 5 minus E 5

Activity
Time(weeks)
Immediate Predecessor(s)
Activity
Time(weeks)
Immediate Predecessor(s)
A
5
minus
E
5
B
B
7
minus
F
7
B
C
4
A
G
11
C, E
D
2
A
H
8
D, F
Part 2
Dave's earliest start(ES) and earliest finish(EF) are:
Part 3Part 4Part 5Part 6Part 7Part 8Part 9
Activity
ES
EF
A
0
5
B
0
7
C
5
9
D
5
7
E
7
12
F
7
14
G
12
23
H
14
22
Part 10
Dave's latest start(LS) and latest finish(LF) are:
Activity
LS
LF

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions