Question
Activity-Based Product Costing Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these
Activity-Based Product Costing
Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below.
Basic | Advanced | Total | ||||
Units produced | 150,000 | 450,000 | ||||
Prime costs | $11,700,000 | $45,000,000 | $56,700,000 | |||
Machine hours | 150,000 | 750,000 | 900,000 | |||
Engineering hours | 400 | 3,600 | 4,000 | |||
Receiving orders | 500 | 1,500 | 2,000 | |||
Inspection hours | 1,000 | 2,000 | 3,000 | |||
Overhead costs: | ||||||
Machining | $10,800,000 | |||||
Engineering | 2,080,000 | |||||
Receiving | 660,000 | |||||
Inspecting products | 420,000 |
Required:
1. Calculate the four activity rates.
Machining rate | $ per machine hour |
Engineering rate | $ per hour |
Receiving rate | $ per order |
Inspecting rate | $ per hour |
2. Calculate the unit costs using activity rates. Round your answers to the nearest cent.
Unit cost | |
Basic | $ per unit |
Advanced | $ per unit |
Calculate the overhead cost per unit. Round your answers to the nearest cent.
Overhead Cost | |
Basic | $ per unit |
Advanced | $ per unit |
3. If consumption ratios instead of activity rates were used to assign costs instead of activity rates, show the cost assignment for the inspection activity.
Cost assignment | |
Basic | $ |
Advanced | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started