ACTIVITYIMMEDIATE PREDECESSORTIME (WEEKS)A4BA5CA7DA7EB2F C D 6G D F 7HD3I E G H 5 b. What is the critical path? (You may select more than one
C
D
6GD
F
7HD3IE
G
H
5b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 1
- A-C-F-G-I
- A-B-E-I
- A-D-H-I
- A-D-F-G-I
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 2
- B
- C
- D
- G
- E
- F
d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 3
- A-C-F-G-I
- A-B-E-I
- A-D-H-I
- A-D-F-G-I
d-2. What is the earliest completion time for the new critical path?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started