Question
1 Approved Answer
ActivityPredecessorTime ( weeks ) A - - 8 BA 6 C - - 4 DC 9 EA 1 1 FB 3 GD , E ,
ActivityPredecessorTimeweeksABACDCEAFBGD E FUsing Table what is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date?Question Select one:Athree activitiesB.two activitiesC.four or more activitiesD.one activity