ACTIVTY ESTIMATED DURATIONS (WEEKS) - Optimistic Most Likely Pessimistic 1-2 3 6 15 1-3 2 5 14 1-4 6 12 30 2-5 2 5 8
ACTIVTY | ESTIMATED DURATIONS (WEEKS) | |||
- | Optimistic | Most Likely | Pessimistic | |
1-2 | 3 | 6 | 15 | |
1-3 | 2 | 5 | 14 | |
1-4 | 6 | 12 | 30 | |
2-5 | 2 | 5 | 8 | |
2-6 | 5 | 11 | 17 | |
3-6 | 3 | 6 | 15 | |
4-7 | 3 | 9 | 27 | |
5-7 | 1 | 4 | 7 | |
6-7 | 4 | 19 | 28 |
a) FIND CRITICAL PATH FOR THE PROJECT
B) FIND EXPECTED PROJECT DURATION