Question
1 Approved Answer
Actual FOH 287,000.00 Direct Material Cost 300,000.00 Direct Labour Cost for 14000 Hours 260,000.00 FOH is @ Rs.20 Per Direct Labour Hour 280,000.00 90% of
Actual FOH 287,000.00 Direct Material Cost 300,000.00 Direct Labour Cost for 14000 Hours 260,000.00 FOH is @ Rs.20 Per Direct Labour Hour 280,000.00 90% of the Job was Completed and Sold 25% above cost on credit Work in Process Opening Rs 11,000 Finished Goods Opening Rs 12,000 Work in Process Ending Rs 18,000 Finished Goods Ending Rs 14,000 Actual FOH 287,000.00 Direct Material Cost 300,000.00 Direct Labour Cost for 14000 Hours 260,000.00 FOH is @ Rs.20 Per Direct Labour Hour 280,000.00 90% of the Job was Completed and Sold 25% above cost on credit Work in Process Opening Rs 11,000 Finished Goods Opening Rs 12,000 Work in Process Ending Rs 18,000 Finished Goods Ending Rs 14,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started