Actual: Units 1000 Direct material purchased 13 000 kilograms @ $1.6 per kilogram Direct material used 10 000 kilograms Direct labour 2 000 hours @
Actual:
Units 1000
Direct material purchased 13 000 kilograms @ $1.6 per kilogram
Direct material used 10 000 kilograms
Direct labour 2 000 hours @ $20 per hour
Standards:
Direct material 11 kilograms @ $1.5 per kilogram
Direct labour hours 2.5 hours @ $15 per hour
How to use Excel file to calculate the direct material and direct labor variances for the above question? Use Excel formulas to determine whether each variance is favorable or unfavorable.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started