Actual variable overhead $10,000 Budgeted variable overhead $12,000 Budgeted production 500 units Actual production 450 units Actual hours 200 Standard time for 1 unit 30
Actual variable overhead $10,000 Budgeted variable overhead $12,000 Budgeted production 500 units Actual production 450 units Actual hours 200 Standard time for 1 unit 30 minutes Among the given options, determine variable overhead efficiency variance. a. $1,200 favorable. b. $1,200 unfavorable c. $1,250 favorable d. $2,400 favorable