Adler Construction CO. uses the percentage-of-completion method. In 2014, Adler began work on a contract for $6,600,000 and it was completed in 2015. Data on
Adler Construction CO. uses the percentage-of-completion method. In 2014, Adler began work on a contract for $6,600,000 and it was completed in 2015. Data on the costs are:
Year ended December 31 | 2014 | 2015 |
Costs Incurred | 2,340,000 | 1,680,000 |
Estimated costs to complete | 1,560,000 |
For the years 2014 and 2015, Adler should recognize gross profit of?