Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Advantage Energy Technology Data Center Migration * - Part A in Chapter 6 on page 2 0 2 . Brian Smith, network administrator at Advanced

Advantage Energy Technology Data Center Migration*- Part A in Chapter 6 on page 202. Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly com- petitive petroleum industry. AET is one of five national software companies that Case 6.1 Em Advantage Energy Technology Data Center Migration-Part A provide an accounting and business management package for oil jobbers and gasolina distributors. A few years ago, AET jumped into the application service provider world. Their large data center provides clients with remote access to AET's complete suite of application software systems. Traditionally, one of AET's primary competi tive advantages has been the company's trademark IT reliability. Due to the complex: ity of this project, Brian will have to use a parallel method of implementation Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised. Currently, AET's data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis Interna- tional Airport. On February 1, Brian is formally assigned the task by the Vice Presi dent of Operations, Dan Whitmore, with the following guidelines: From start to finish, it is anticipated the entire project will take three to four months to complete. It is essential that AET's 235 clients suffer no downtime. Whitmore advises Brian to come back to the Executive Committee on February 15. with a presentation on the scope of the project that includes costs, "first-cut" timeline. and proposed project team members. Brian had some preliminary discussions with some of AET's managers and dire tors from each of the functional departments and then arranged for a full-day scope * Prepared by James Moran, a project management instructor at the College of Business, Oregon State UniversityChapter 6 Developing a Project Plan 203 meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following Three to four months is a feasible project timeline and first-cut cost estimate is $80,000 $90,000(this includes the infrastructure upgrade of the new site). Critical to the no-downtime" requirement is the need to completely rely on AET'S remote disaster recovery "hot" site for full functionality. Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service. Brian's Executive Committee report was positively received and, after a few modifica- tions and recommendations, he was formally charged with responsibility for the proj- cet, Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process. Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the net- work. Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires A new ventilation system. The manufacturer's requirements include an ambient tem- perature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time, The data center supervisor requested that Brian replace all of the old power sup- plies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that con- struction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to Install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units ("Switchover Approval"). Meetings with each of the functional units will require one week. During this time he an initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day, Upon completion of the power check, he can take one week to install his test servers. The best servers will test all of the primary network functions and act as a safeguard Sefore the network is taken offline. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infra- structure is safe, which will take two days. Then they will sign off the Primary Systems heck, taking one day of intense meetings. They will also set an official date for the wetwork moveBrian is happy that everything has gone well thus far and is convinced that the move will go only. Now that an official date is set, the network will be shut down for a day Inn must move all of the network components to the new data center Brian will do the move over the weekend two days when user traffic is at low point ASSIGNMENT holiday 1. Generate a prionty matrix for ALTA system move, 2. Develop a Wess for Brian's project, include duration (days) and predecessors. 3. Using a project planning tool, generate a network diagram for this project. Note Base your plan on the following guidelines: eight-hour days, five-day weeks except for when Brian moves the network components over a weekend, no bronks, March 1,2010, is the project start date, Ordering Ventilation System, New Racks, and Power Supplies Cables takes only one actual day of work. The remain- ing days are the time necessary for the vendors to fill and ship the order to Brian Souse fish to Start lags here. Assume that live days after the start of the Renova- tion of the Data Center that the raised floor will be ready for inspection (a Start-to-

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology And Management

Authors: Eric G. Bolen, William Laughlin Robinson

5th Edition

013066250X, 978-0130662507

More Books

Students also viewed these General Management questions

Question

Design a health and safety policy.

Answered: 1 week ago