After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative.
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status? Behind schedule On schedule Ahead of schedule Stopped