Question
After successfully completing your project management class at NJIT, you have decided to put together a (1) Work Breakdown Structure (WBS) and (2) Responsibility Assignment
After successfully completing your project management class at NJIT, you have decided to put together a (1) Work Breakdown Structure (WBS) and (2) Responsibility Assignment Matrix (RAM) in order to help you plan for the event. Your WBS (Level 1) must include:
- Obtaining a banquette hall
- Getting a host / Master of ceremonies
- Sending invitations out and responses in
- Securing entertainment
- Food and drink
- Decorations
(1) Construct a WBS (Table Format) using the above-mentioned actives as Level 1 with two (2) additional Levels of decomposition that you are to develop.
WBS Table Format w Level 1 Activities
Tribute Dinner | ||
Level | WBS | Name |
1 | 1 | Obtaining a Banquette Hall |
1 | 2 | Getting a host / Master of Ceremonies |
1 | 3 | Sending Invitations Out and Responses In |
1 | 4 | Securing Entertainment |
1 | 5 | Food and Drink |
1 | 6 | Decorations |
(2) Build a RAM using the activities from the lowest level of your WBS, assigning levels of responsibility to the following groups/individuals:
- Banquette Organizer
- Catering Hall
- Entertainment Director
- Procurement Director
The levels of responsibilityare:
- Responsible (R) - Performing the work
- Accountable (A) - Ensuring completion
- Consulted (C) - Consulted regarding Decisions
- Inform (I) - Informed
Banquette Organizer | Catering Hall | Entertainment Director | Procurement Director | |
Activities from the lowest level of the WBS | ||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started