Question
Agile Mindset is Select one: A. 4 Values, 12 Principles, Many Practices B. 4 Values, 12 Principles C. 4 Values, 10 Principles, Many Practices D.
- Agile Mindset is Select one:
A. 4 Values, 12 Principles, Many Practices
B. 4 Values, 12 Principles
C. 4 Values, 10 Principles, Many Practices
D. 4 Values, Many Practices
2. Agile is a iterative / incremental process
Select one:
True
False
3,Which of these elements are normally included in the business case to justify the project?
Select one:
A. Cost-Benefit Analysis
B. Schedule Baseline
C. Critical Path
D. Cost Baseline
4.A project may be authorized by any of the following except
Select one:
A. PMO
B. Product Owner
C. Project Sponsor
D. IT Executive
5. The artifact used to identify stakeholders that can provide information on detailed project and product requirements.
Select one:
A. Project Charter
B. Risk Register
C. Communication Plan
D. Stakeholder Register
6. The process of defining how to conduct risk management activities for a project.
Select one:
a. Monitor Risks
b. Control Risks
c. Plan Risk Management
d. Project Plan
7. Cross Training is used to
Select one:
A. Get Resources
B. Identify Stakeholders
C. Provide Role Clarification
D. Assign Resources
8. In the Close Project or Phase process, organizational process assets are considered a(n)
Select one:
A. Input
B. Output
C. Input & Output
D. Asset
9. Product owner owns
Select one:
A. Product Backlog
B. Scrum Backlog
C. Project Charter
D. Project Plan
10. Retrospective is
Select one:
A. Scrum Ceremony
B. Agile Artifact
C. Part of Project Plan
D. Part of Communication Plan
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started