AI answer ... Chose the correct answer: Question 6 Not yet answered Marked out of 1.00 Flag question Question text Project teams characterize risk by
AI answer ... Chose the correct answer: Question 6 Not yet answered Marked out of 1.00 Flag question Question text Project teams characterize risk by impact and likelihood. Which quadrant is high impact and low likelihood? Question 6Select one: a. i. Major b. ii. Critical c. iii. Minor d. iv. Major