a)Jenga Limited is considering undertaking a project which requires the following resources: Activity Preceding Activity Normal time(days) Crash time(days) Total cost (Sh.000) A - 7
a)Jenga Limited is considering undertaking a project which requires the following resources:
Activity
Preceding Activity
Normal time(days)
Crash time(days)
Total cost (Sh.000)
A
-
7
5
7,500
B
-
6
3
6,000
C
-
2
2
2,500
D
A
5
4
6,000
E
B
5
4
7,000
F
E
6
2
8,000
G
E
7
6
6,000
H
C
6
5
7,200
I
H
8
5
9,800
J
D
4
4
3,500
K
J
6
5
3,600
L
F
3
2
7,000
M
G,I
8
4
9,200
N
K,L,M
4
2
7,700
The overheads costs of the project amount to Sh.500 per day while the cost of crashing an activity per day is sh. 1,000.
Required:
i)A network diagram for the project.(6 marks)
ii)The project's normal completion time, normal cost and critical path of the project.(4 marks)
iii)The minimum time in which the project could be completed and the cost of the project.(6 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started