Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

a)Jenga Limited is considering undertaking a project which requires the following resources: Activity Preceding Activity Normal time(days) Crash time(days) Total cost (Sh.000) A - 7

a)Jenga Limited is considering undertaking a project which requires the following resources:

Activity

Preceding Activity

Normal time(days)

Crash time(days)

Total cost (Sh.000)

A

-

7

5

7,500

B

-

6

3

6,000

C

-

2

2

2,500

D

A

5

4

6,000

E

B

5

4

7,000

F

E

6

2

8,000

G

E

7

6

6,000

H

C

6

5

7,200

I

H

8

5

9,800

J

D

4

4

3,500

K

J

6

5

3,600

L

F

3

2

7,000

M

G,I

8

4

9,200

N

K,L,M

4

2

7,700

The overheads costs of the project amount to Sh.500 per day while the cost of crashing an activity per day is sh. 1,000.

Required:

i)A network diagram for the project.(6 marks)

ii)The project's normal completion time, normal cost and critical path of the project.(4 marks)

iii)The minimum time in which the project could be completed and the cost of the project.(6 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions