Ajob was budgeted to require 5 hours of labor per unit at $11.00 per hour. The job consisted of 7,500 units and was completed in
Ajob was budgeted to require 5 hours of labor per unit at $11.00 per hour. The job consisted of 7,500 units and was completed in 36,500 hours at a total labor cost of $415,600. What is the total labor cost variance? Multiple Choice points (8 00:37:27 ) $3,100 untavorable. $6.475 unfavorable. ooooo $2975 urtovarable $3,375 unfavorable. $620 unfavorable. O $7,500 unfavorable