Question
Albedo Company made the following acquisitions during the year: Purchased for P5,400,000 a warehouse building and the land on which is located. The land had
Albedo Company made the following acquisitions during the year:
Purchased for P5,400,000 a warehouse building and the land on which is located. The land had an appraised value (fair market value) of P2,000,000 and original cost of P1,400,000. The building had an appraised value of P3,000,000 and original cost of P2,800,000.
Purchased an office building and the land on which it is located for P7,500,000 cash and assumed an existing P2,500,000 mortgage. For realty tax purposes, the property is assessed at P9,600,000, 60% of which is allocated to the building.
What is the amount should be reported as total cost of land and building, respectively?
Albedo Company made the following acquisitions during the year:
Purchased for P5,400,000 a warehouse building and the land on which is located. The land had an appraised value (fair market value) of P2,000,000 and original cost of P1,400,000. The building had an appraised value of P3,000,000 and original cost of P2,800,000.
Purchased an office building and the land on which it is located for P7,500,000 cash and assumed an existing P2,500,000 mortgage. For realty tax purposes, the property is assessed at P9,600,000, 60% of which is allocated to the building.
What is the amount should be reported as total cost of land and building, respectively?
P6,160,000 and P9,240,000
P6,000,000 and P9,000,000
P5,840,000 and P8,760,000
P5,000,000 and P7,760,000
Question at position 35
35
1 point
Question 35 is unpinned. Click to pin.
Question at position 35
1. Chongyun Company incurred the following costs during the current year:
Tax in arrears on land | P50,000 |
Payment for the land | 1,000,000 |
Architect fees | 230,000 |
Contract price for factory building | 5,000,000 |
Safety fence around construction site | 35,000 |
Safety inspection on building | 30,000 |
Removal of safety fence after the completion of building | 20,000 |
New fence surrounding the factory | 80,000 |
Driveway, parking bay, and safety lighting | 550,000 |
Trees, shrubs, and other landscaping | 200,000 |
What amount should be recorded as cost of land improvements?
1. Chongyun Company incurred the following costs during the current year:
Tax in arrears on land | P50,000 |
Payment for the land | 1,000,000 |
Architect fees | 230,000 |
Contract price for factory building | 5,000,000 |
Safety fence around construction site | 35,000 |
Safety inspection on building | 30,000 |
Removal of safety fence after the completion of building | 20,000 |
New fence surrounding the factory | 80,000 |
Driveway, parking bay, and safety lighting | 550,000 |
Trees, shrubs, and other landscaping | 200,000 |
What amount should be recorded as cost of land improvements?
P630,000
P750,000
P280,000
P830,000
Question at position 36
36
1 point
Question 36 is unpinned. Click to pin.
Question at position 36
Expensed or Capitalized: Cost of employee benefits arising directly from the acquisition of property, plant, and equipment.
Expensed or Capitalized: Cost of employee benefits arising directly from the acquisition of property, plant, and equipment.
Capitalized
Expensed
Question at position 37
37
1 point
Question 37 is unpinned. Click to pin.
Question at position 37
1. The recognition criteria for an intangible asset include which condition?
1. The recognition criteria for an intangible asset include which condition?
It Is probable that future economic benefit will arise from use and the cost can be reliably measured.
It is probable that future economic benefit will arise.
The cost can be measured reliably.
The intangible asset must be measured at cost.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started