All information needed to solve this problem is present Problem 9-24 (Algorithmic) Office Automation, Inc., developed a proposal for introducing a new computerized office system
All information needed to solve this problem is present
Problem 9-24 (Algorithmic)
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:
Immediate | Time (weeks) | Cost ($1000s) | |||||||
Activity | Description | Predecessor(s) | Normal | Crash | Normal | Crash | |||
A | Plan needs | 9 | 8 | 30 | 50 | ||||
B | Order equipment | A | 8 | 6 | 120 | 150 | |||
C | Install equipment | B | 10 | 7 | 100 | 160 | |||
D | Set up training lab | A | 7 | 6 | 40 | 50 | |||
E | Conduct training course | D | 10 | 8 | 50 | 75 | |||
F | Test system | C, E | 3 | 3 | 60 |
- Which project network is correct?
(i) (ii) (iii) (iv) - Develop an activity schedule. If your answer is zero, enter 0.
Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity (Yes or No) A B C D E F - What are the critical activities, and what is the expected project completion time? Critical Path: Expected project completion time = _____ weeks.
- Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
Crash Activities Number of Weeks Cost ($1000s) A 1 B 2 C 1 D 1 E 1 - Develop an activity schedule for the crashed project. If your answer is zero, enter 0.
Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity (yes or no) A B C D E F - What added project cost is required to meet the six-month completion time? Total added cost due to crashing $ _______.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started