All of the following are objectives of PERT/CPM EXCEPT Part 2 A. help map out a plan of the project to better understand where the
All of the following are objectives of PERT/CPM EXCEPT Part 2 A. help map out a plan of the project to better understand where the project team is going visually B. determine how long it should take to finish a project C. find out which tasks require tight control and which can more easily be delegated D. brainstorm project ideas