All of the following are required for decisions concerning crashing except A list of all the activities. Information about regular time and crash time estimates
All of the following are required for decisions concerning crashing except
A list of all the activities.
Information about regular time and crash time estimates for each activity.
A list of activities that are on the critical path.
Information about regular cost and crash cost estimates for each activity.