All of the following criteria can be used to categorize project risks EXCEPT: whether the risk is a known risk the project objective that may
All of the following criteria can be used to categorize project risks EXCEPT:
whether the risk is a known risk | ||
the project objective that may be impacted by the risk | ||
whether the risk is internal or external to the performing organization | ||
the project life cycle phase |