An activity E has thee immediate successors M, P, and R (that is, M, P, and R have E as one of their immediate predecessors).
An activity E has thee immediate successors M, P, and R (that is, M, P, and R have E as one of their immediate predecessors). The latest finish times for M, P, and R are 22, 15, and 20 weeks, and each of them takes 4 weeks to complete. If E takes 5 weeks to complete, what is the latest start time (in weeks) for E?
Step by Step Solution
There are 3 Steps involved in it
Step: 1