Question
An activity has a duration estimate that is best case = 5 days, most likely = 12 days, and worst case=15 days. What is
An activity has a duration estimate that is best case = 5 days, most likely = 12 days, and worst case=15 days. What is the Triangular three-point estimate for this activity in days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
The Triangular threepoint estimate for the activity can be calculated by using the formula Triang...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
International Financial Reporting and Analysis
Authors: David Alexander, Anne Britton, Ann Jorissen
5th edition
978-1408032282, 1408032287, 978-1408075012
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App