Question
1 Approved Answer
An activity has an early start (ES) of day 6, a late start (LS) of day 16, and early finish (EF) of day 10, and
An activity has an early start (ES) of day 6, a late start (LS) of day 16, and early finish (EF) of day 10, and a late finish (LF) of day 20. The activity:
1. is not on the critical path
2. is on the critical path
3. is progressing well
4. has a lag