An activity has an early start of 2 days, late start of 12 days, early finish of 9 days and late finish of 19 days.
An activity has an early start of 2 days, late start of 12 days, early finish of 9 days and late finish of 19 days. What is the duration of this activity?
A)
2 days
B)
7 days
C)
8 days
D)
10 days