An activity has an early start of 2 days, late start of 12 days, early finish of 9 days and late finish of 19 days.

An activity has an early start of 2 days, late start of 12 days, early finish of 9 days and late finish of 19 days. What is the duration of this activity?

A)

2 days

B)

7 days

C)

8 days

D)

10 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Marketing The Ultimate Marketing Tool

Authors: Edward L. Nash

1st Edition

0070460639, 978-0070460638

More Books

Students also viewed these Databases questions