An activity on a PERT network has these time estimates: optimistic = 2 , most likely = 3 , and pessimistic = 8 . What

An activity on a PERT network has these time estimates: optimistic =2, most likely =3, and pessimistic =8. What is its expected activity time and variance?
Select one:
a.3.67;1
b.3.67;6
C.4.33;6
d.4.33;1
e. None of these
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Nigel Slack, Stuart Chambers, Robert Johnston

6th edition

273731602, 978-0273731603

More Books

Students also viewed these General Management questions

Question

4.1 What is public choice theory?

Answered: 1 week ago