Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

An analysis has been undertaken by the industrial engineering staff in consultation with the activity managers.The activity listed below can be crashed. Reduce the project

An analysis has been undertaken by the industrial engineering staff in consultation with the activity managers.The activity listed below can be crashed. Reduce the project duration as much as cost justified by crashing selected activities. Remember, you must crash the whole activity and that the crashing ranking is 1) Critical Path, 2) Lowest Crash Cost, 3) Earliest in the Project

1. Develop & Issue Computer Hardware RFP

A Subcontractor can assist with the writing of the hardware RFP, such that the activity duration can be reduced from 6 days to 3 days for an added cost of $2,000 to the activity.

2. Software Documentation

The software vendor can reduce the duration of this activity from 8 days to 4 days through the use of additional staffing and overtime, at a cost of $3,500.

3. Post Systems Manager Position Announcement

As per TC policy, the posting period for the new systems manager position can be reduced form 10 days to 3 days by using overnight and electronic mailing of the announcement to all TC locations, and accepting electronic applications. The added cost to the activity would be $3,000

4. Modify Software

The Software vendor can work weekends and overtime to make the required software modifications. The activity time can be reduced from 15 days to 5 days, for an added cost of $5,000 to the activity.

5. Associate Training

By training over the weekend, TC can reduce the training activity time from 5 days to 3 days at an additional activity cost of $7,000 in overtime and expenses. This option may create serious quality problems.

6. Relocate Systems Manager

The new systems manager can be housed at additional expense in a hotel temporarily to reduce relocation time from 10 to 8 days. The added cost to the activity would be $4,000.

7. Construct Building Space

The conversion of the building space can be accomplished by a subcontractor, working 24 hours a day, with a reduction in construction time from 6 to 3 days for an added activity cost of $2,000.

I need help creating a crash table and a network diagram with the information above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Theory And Practice

Authors: John A. Parnell

4th Edition

1452234981, 9781452234984

More Books

Students also viewed these General Management questions

Question

Are the hours flexible or set?

Answered: 1 week ago

Question

2. Ask questions, listen rather than attempt to persuade.

Answered: 1 week ago