An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are

An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times:

TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS) TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS)
a 48 g d 43
b 58 h e 38
c 73 i f 23
d a 63 j g 33
e b 88 k h, i 53
f c 23 l j, k 67

Assign tasks to workstations using the longest operating time and calculate the idle time for each workstation. (Leave no cells blank - be certain to enter "0" wherever required.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P. Robbins, Mary A. Coulter

12th edition

133043606, 978-0133043600

More Books

Students also viewed these General Management questions