Question
1 Approved Answer
. An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 450 units per day. Here
An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times: TASK A PRECEDING TASKS PERFORMANCE TIME (SECONDS) 40 C R 25 15 D F G H. I J, K 10 b. What is the workstation cycle time required to meet the desired output rate? Workstation cycle time 67 seconds per unit c. What is the theoretical minimum number of workstations required to meet the desired output rate? Note: Round up your answer to the next whole number. Minimum number of workstations d. Assign tasks to workstations using the longest task time. Note: Leave no cells blank - be certain to enter "0" wherever required. Work Station Task Idle Time 1 2 3 4 5 F e. What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b? Note: Round your answer to 1 decimal place. Efficiency % . Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 8.5 hours per day using regular time. Note: Round your answer for cycle time down to the nearest whole number. Round your answer for overtime up to the nearest whole number. cycle time to seconds per unit. Another option is to work minutes overdore.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started