An assembly line with 20 activities is to be balanced. The total amount of time to complete all 20 activities is 45 minutes. The longest
An assembly line with 20 activities is to be balanced. The total amount of time to complete all 20 activities is 45 minutes. The longest activity takes 3.0 min and the shortest takes 0.5 min. The line will operate for 450 minutes per day. What is the maximum daily output that can be achieved by this assembly line?
Step by Step Solution
There are 3 Steps involved in it
Step: 1