An assembly line with 3 0 activities is to be balanced. The total amount of time to complete all 3 0 activities is 4 0

An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 40 minutes. The longest activity takes 2.0 minutes and the shortest takes 0.7 minute. The line will operate for 360 minutes per day.
What are the maximum and minimum cycle times? Round your answers to one decimal place.
Maximum cycle time:
minutes
Minimum cycle time:
minutes
How much daily output will be achieved by each of those cycle times? Round your answers to the nearest whole number.
Daily output achieved by maximum cycle time:
units/day
Daily output achieved by minimum cycle time:
units/day

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Research Applications And Algorithms

Authors: Wayne L. Winston

3rd Edition

0534520200, 9780534520205

More Books

Students also viewed these General Management questions

Question

Explain the different types of marketing strategies.

Answered: 1 week ago

Question

Explain product positioning.

Answered: 1 week ago

Question

Explain Industrial market segment.

Answered: 1 week ago