Question

1 Approved Answer

An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project with an estimated final cost (BAC) of $8.45 million.

An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project with an estimated final cost (BAC) of $8.45 million. The values at the data date are as follows: EV = $5.25M, AC = $4.95M, and PV = $6.50M.

What are the cost and schedule variances and indices?

What is the projected final cost (EAC)?

All things being equal, what will be the final duration (FD)?

It is acceptable to use SPI to estimate the FD.

What can be concluded from the EVA at this point?

PLEASE SHOW STEPS

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions